Works Summary
Construction of Robert Street and Black Street, Lilydale includes approximately 137 metres urban standard asphalt road generally 3.5 metres trafficable width following the existing road formation. Centrally located concrete spoon drain and grated pits connecting to existing underground drainage in Black Street.
Background
In 2019 the Federal Government announced a nine year, $150 million funding plan for Yarra Ranges Council to seal roads within the Dandenong Ranges and surrounding areas. This funding program has been named the Roads for the Community Initiative.
Council has prioritised roads that will be constructed through this program to ensure funding is used in a way that will provide maximum benefit to the greatest number of residents and visitors to our area. For information explaining how priority was assigned, please see Roads for the Community FAQ's.
This project has been listed for construction under the Roads for the Community Initiative program and will be facilitated by means of a Special Charge Scheme, whereby landowners and Council form a partnership to fund construction.
Project Timeline
-
Timeline item 1 - complete
Landowner consultation
- Questionnaire sent to all landowners affected to gauge your support for proposal.
- Special Charge Scheme road construction projects only proceed where both Council and a majority of landowners are supportive of the proposal.
-
Timeline item 2 - complete
Design
- Council’s Project Engineer will coordinate feature survey and design
-
Timeline item 3 - complete
Landowner briefing
- Accessible online via Council’s website.
- Invitation letter sent to landowners
- The briefing will outline design and Special Charge Scheme Statutory process.
Watch the landowner briefing
-
Timeline item 4 - complete
Intent to levy
- Report to Council 28 September 2021 View agenda & minutes
- Intent to Levy Notice sent to landowners
- Landowners may submit formal submissions
- Review of submissions
- Report to Council with submissions 23 November 2021 View agenda & minutes
-
Timeline item 5 - complete
Declaration
- Declaration of Special Charge Scheme Notice sent to landowners
- Landowners may apply for Council’s Declaration of the Special Charge to be reviewed at VCAT
- If no appeals to VCAT the project will be tendered
- If an appeal is lodged at VCAT the project will be put on hold until a written decision has been made
-
Timeline item 6 - complete
Construction
- Contractor engaged via tender
- Notification of works commencement letter sent to landowners
- Works complete
-
Timeline item 7 - complete
Final Cost
- Final costs of project reported to Council 13 August 2024 View agenda & minutes
- Letter sent to landowners to notify final cost