Before
After
Works Summary
Proposed works for Old Coach Road (from no.12 to no.37), Montrose:
- Approximately 760 metres of asphalt pavement following the existing road alignment.
- Existing table drains reshaped and lined with cement treated crushed rock.
Background
In 2016, landowners petitioned to Council for the construction of Old Coach Road (from no.12 to no.37), Montrose as a special charge scheme.
In March 2021, landowners along Old Coach Road (from no.12 to no.37), Montrose were surveyed to determine their support for a special charge scheme to construct the road.
A majority of landowners supported the proposal and the project has since been referred for inclusion in Council’s forward 10-year Capital Expenditure Program (CEP).
Projects are prioritised according to Council’s current commitments, priorities and funding levels. The CEP is reviewed on an annual basis in order to cater for current priorities.
Landowners will be further advised of the status of the project, after Council consider the draft CEP in June 2022.
Project Timeline
-
Timeline item 1 - complete
Landowner consultation
- Questionnaire sent to all landowners affected to gauge your support for proposal.
- Special Charge Scheme road construction projects only proceed where both Council and a majority of landowners are supportive of the proposal.
Landowner survey complete.
-
Timeline item 2 - complete
Design
- Council’s Project Engineer will coordinate feature survey and design
-
Timeline item 3 - complete
Landowner briefing
- Accessible online via Council’s website.
- Invitation letter sent to landowners
- The briefing will outline design and Special Charge Scheme Statutory process.
- Transcript available in related links
-
Timeline item 4 - complete
Intent to levy
- Report to Council - 24 May 2022 View agenda & minutes
- Intent to Levy Notice sent to landowners
- Landowners may submit formal submissions
- Review of submissions
- Report to Council with submissions - 26 July 2022 View agenda & minutes
-
Timeline item 5 - complete
Declaration
- Declaration of Special Charge Scheme Notice sent to landowners
- Landowners may apply for Council’s Declaration of the Special Charge to be reviewed at VCAT
- If no appeals to VCAT the project will be tendered
- If an appeal is lodged at VCAT the project will be put on hold until a written decision has been made
-
Timeline item 6 - active
Construction
- Contractor engaged via tender
- Notification of works commencement letter sent to landowners
- Works complete
-
Timeline item 7 - incomplete
Final Cost
- Final costs of project reported to Council
- Letter sent to landowners to notify final cost
Contact Us
Have questions or want to learn more about a project, contact us below: