Construction Works Update

30 May 2023

Road construction and sealing works along Valley Road are now complete and when the tender for construction was awarded, it was anticipated both roads would be constructed consecutively. However, the contractor had to pause works for operational reasons which has caused a construction delay of School Road.

Construction works for School Road, Seville are now scheduled to commence in early July 2023 and should take approximately 2-3 months to complete subject to favourable conditions.

Important information:

  • Works occur between Monday – Friday, 7.30am to 4.30pm (can vary)
  • Traffic may be halted for up to 15 minutes
  • Emergency access and services will remain for residents
  • Weekly waste collection services will be earlier (around 6am)
  • Do not leave vehicles parked on roadside when property unattended
  • Keep your speed under 40km/h
  • Be prepared to stop as you approach the works
  • Follow directions given by works personnel and/or traffic controllers
  • Council will be undertaking inspections (almost daily)
  • Driveways will be reinstated as close to their current standard

Please note, the contractor will inform residents of any major disruptions to driveway and/or road access during the works so please keep an eye on your mailbox for notices from the contractor.

Council has appointed Foley Services Pty Ltd as the contractor for these works, with Mick Foley (0418 512 346) being the Contractor Site Supervisor.

Should you have any queries regarding these works, you can contact the Project Engineer – John Williams on 1300 368 333.