News

Construction Works Notification

3 January 2023

Road Construction Works along Grandview Crescent and Lawrence Court, Healesville are scheduled to commence the week beginning 2 January 2023 and should take approximately 12-15 weeks to complete subject to favourable conditions.

Please be aware that while we will make every attempt to keep disruptions to a minimum, due to the nature and extent of the works there are likely to be some disruptions to access and traffic flow. This will occur during normal construction working hours from 7.30 am to 4.30 pm on weekdays.

Emergency access for local residents will remain a priority; however, there will be occasions throughout the day when traffic flow will be temporarily halted for up to 15 minutes.

Where the proposed works affect a driveway, the affected area will be reinstated as close as possible to its current standard. The contractor undertaking the works will inform residents of any disruptions to driveway access during the works.

During this period could you please ensure no vehicles are left parked on the roadside when your household (or organisation) is left unattended.

As there will be workers and equipment operating in close proximity to traffic, for the safety of all we request that you:

  • Keep your speed under 40km/h;
  • Be prepared to stop as you approach the works; and
  • Follow directions given by works personnel and / or traffic controllers.

As a matter of added safety, children are advised to keep away from the works throughout the duration.

During construction works, we request that:

  • People do not ride bicycles or walk on new concrete.
  • Motor vehicles do not drive over any new concrete for 3-5 days after pouring.
  • Heavy vehicles do not drive over any new concrete for 14 days after pouring.

Please inform any others within your household (or organisation) likely to be affected by these works of the above details.

Council has appointed Dallum Constructions as the contractor for these works, with Albert D’Alessandro (0412 011 334) being the contractor’s site supervisor.