Before
After
Chaundy Road has been designed to be constructed with an asphalt seal and existing open drains.
The works include the construction of 335 metres of road with a 3.5-metre trafficable seal.
The road will follow the existing formation to minimise the removal of existing vegetation. The road is sloped towards the high side, allowing stormwater to sheet flow to the high side of the road. From there, it will be collected by the existing open table drain and connected to the drainage network at Mt Morton Road.
Project timeline
-
Timeline item 1 - complete
Landowner consultation
- Questionnaire sent to all landowners affected to gauge your support for proposal.
- Special Charge Scheme road construction projects only proceed where both Council and a majority of landowners are supportive of the proposal.
Landowner survey complete.
-
Timeline item 2 - complete
Design
- Council’s Project Engineer will coordinate feature survey and design
-
Timeline item 3 - complete
Landowner briefing
- Accessible online via Council’s website.
- Invitation letter sent to landowners
- The briefing will outline design and Special Charge Scheme Statutory process.
Watch the landowner briefing
-
Timeline item 4 - complete
Intent to levy
- Report to Council 14 September 2021 View Agenda and Minutes
- Intent to Levy Notice sent to landowners. View the Intent to Levy Public Notice.
- Landowners may submit formal submissions
- Review of submissions
- Report to Council with submissions 23 November 2021 View Agenda and Minutes
-
Timeline item 5 - complete
Declaration
- Declaration of Special Charge Scheme Notice sent to landowners
- Landowners may apply for Council’s Declaration of the Special Charge to be reviewed at VCAT
- If no appeals to VCAT the project will be tendered
- If an appeal is lodged at VCAT the project will be put on hold until a written decision has been made
-
Timeline item 6 - complete
Construction
- Contractor engaged via tender
- Notification of works commencement letter sent to landowners
- Works complete
-
Timeline item 7 - incomplete
Final Cost
- Final costs of project reported to Council
- Letter sent to landowners to notify final cost